28 Marlboro Real Estate Project

Current RCG Real Estate Investment Property

ACTIVE: We have broken ground! Stay tuned for updates and new pictures! And be sure to follow us on Social Media for updates as well.

 

TIMELINE TASK PROJECTED DATE ACTUAL DATE
Walk through property  2/25/24  2/25/24
 Offer Accepted  3/1/24  3/1/24
 P&S  3/5/24  3/11/24
 Appraisal  5/1/24  5/28/24
Approve Construction Drawings 8/5/24 8/8/24
 Schematic & Elevation Design 7/25/24  7/25/24
Electric and Internet set up, with Security Cameras 9/20/24 9/20/24
Appliances Removed 9/22/24 9/22/24
Permits Approved submitted application 8/18 approved 9/28
Security Fencing installed 9/30/24 9/30/24
Tree & Shrub Removal 10/1/24 10/1/24
Demolition  10/7/24

10/7/24, COMPLETED as of 10/18/24

Excavation 10/28/24 10/22/24
Foundation Work 11/4/24
Framing 11/25/24
Roofing by 12/30/24
Windows & Doors by 12/30/24
Plumbing ongoing
Electrical

ongoing

HVAC
Kitchen
Finish Carpentry
Hardscape/Landscape
Finish Construction  7/1/25
Staging  7/5/25
Pictures for Listing  7/7/25
Private Open House for Investors  TBD
Private Open House for Neighbors  TBD
Property Listen on Market  7/10/25
 Closing  8/14/25

To be added to our mailing list for updates on current RCG real estate projects, or if you’d like an offer on your property with potential, please email us at jill@rennellcapitalgroup.com with all of your contact information so we can keep in touch.

interested in collective real estate investing opportunities?

reach out to rcg